Vice Chairman Nguyễn Ngọc Sâm inspects Đăk Tờ Kan Riverbank Protection Project

On October 29, Vice Chairman of the Provincial People’s Committee Nguyễn Ngọc Sâm inspected construction progress on the Đăk Tờ Kan Riverbank Protection Project in Đăk Tô Commune.

Vice Chairman Nguyễn Ngọc Sâm inspects the project’s site

The project has a total investment of more than VNĐ183 billion, including VNĐ180 billion from the central budget and VNĐ3.5 billion from the local budget. It involves over 7 km of embankments along both riverbanks, aimed at improving flood drainage, preventing erosion and protecting residents, property and farmland.

According to the commune authorities, the eastern-bank embankment has reached approximately 96 per cent completion and is expected to be handed over for use in November 2026. Construction on the western-bank section has reached around 15 per cent. All land required for the project has been handed over, with no outstanding clearance issues or land disputes.

The project’s site

To date, the project has been allocated VNĐ127.7 billion. Of the VNĐ50 billion assigned for 2026, more than VNĐ38.6 billion has been disbursed, equivalent to 77.34 per cent.

Vice Chairman Nguyễn Ngọc Sâm acknowledged the efforts of Đăk Tô Commune and relevant units, particularly in construction and public investment disbursement. He urged the investor and contractors to mobilize sufficient personnel and equipment to accelerate the remaining work and disburse 100 per cent of the assigned annual capital.

He also requested that the eastern-bank embankment undergo technical inspection and be handed over for use within 2026, while the western-bank section should be completed in 2027 to ensure the project delivers its full intended benefits.

Minh Thiện

 