Quảng Ngãi steps up efforts to resolve bottlenecks in two projects in Nghĩa Lộ ward

 

https://quangngai.gov.vn/upload/2006516/fck/ctthuong/1795686072201_1617522402355089059_1617522402355089059_21221ddd8b02f1d73376f30b7d6ee62b.jpg

Vice Chairman of the Provincial People's Committee Nguyễn Công Hoàng chairs the meeting.

Vice Chairman of the Provincial People’s Committee Nguyễn Công Hoàng chaired a meeting on November 26 with relevant departments, agencies and local authorities to review the progress of the Thạch Bích Green Park project and the new urban area project serving resettlement in the second section of the dike.

According to the provincial Civil and Industrial Construction Investment Project Management Board, the Thạch Bích Green Park project has a total investment of VNĐ 900 billion, covering 8.1 hectares.

Scheduled for implementation during 2025-2028, the project includes roads, green spaces, a water plaza, a children's playground, sports facilities and other supporting infrastructure.

 

Land surveys and inventories of trees, crops and existing structures have largely been completed.

Under the first phase of site clearance, nearly 1.2 hectares have been handed over  to the investor, allowing contractors to begin preparatory work and site clearance for construction.

However, compensation and site clearance remain challenging, particularly in verifying land origins and usage history, determining resettlement eligibility for households with multiple generations living together, and addressing previously approved compensation plans for which payments have not yet been received.

Meanwhile, the new urban area project serving resettlement in the second section of the dike covers 8.248 hectares, with a total investment of nearly VNĐ 296.5 billion.

The project aims to develop a resettlement land fund to accommodate approximately 317 households.

Following the handover of project responsibilities, the investor has reviewed legal documents, design and cost estimates, and assessed the remaining construction workload.

Adjustments to the zoning plan and detailed construction plan have been approved, while procedures to select contractors for the remaining work are underway.

https://quangngai.gov.vn/upload/2006516/fck/ctthuong/1795686072174_1617522402355089059_1617522402355089059_b961411248c3c633952a0f706094b7c2.jpg

Vice Chairman of the Provincial People's Committee Nguyễn Công Hoàng delivers the concluding remarks at the meeting.

At the meeting, Vice Chairman Nguyễn Công Hoàng requested the provincial Land Fund Development Centre, the Civil and Industrial Construction Investment Project Management Board and the Nghĩa Lộ ward People's Committee to strengthen coordination and proactively address obstacles affecting both projects.

He stressed that leaders of relevant agencies must directly monitor implementation, provide timely direction and take full responsibility for their assigned tasks.

He also called on relevant departments and agencies to adopt consistent approaches to resolving legal issues, ensuring clear responsibilities and coordinated guidance to prevent inconsistencies from delaying project implementation.

The Vice Chairman further requested relevant units to review implementation results, clearly identify outstanding difficulties and their underlying causes, and propose specific solutions for submission to the Provincial People’s Committee.

He emphasized the need to resolve long-standing issues, safeguard the legitimate rights and interests of residents, and accelerate both projects in line with their approved schedules.

M.H