Quảng Ngãi, November 17, 2026 – Vice Chairman of the Provincial People’s Committee Nguyễn Công Hoàng on November 17 inspected the progress of two major infrastructure projects: the Sa Huỳnh Fishing Port storm shelter anchorage sand barrier, wave reduction and navigation channel dredging project, and the first component of the second phase of the Dung Quất – Sa Huỳnh coastal road project.
The Sa Huỳnh project, with a total investment of VNĐ250 billion (approximately US$10 million), is being implemented from 2023 to 2027.
It includes a 300-metre northern sand barrier and the dredging of a 1,946-metre-long, 40-metre-wide navigation channel.
The northern sand barrier was completed and put into operation on June 27, 2025.
Of the approximately 497,000 cubic metres of dredging planned, contractors have completed around 60,000 cubic metres.
However, the remaining work has been suspended since February 2025 due to difficulties in finding a disposal site for dredged materials.
The existing southern breakwater has also deteriorated, allowing sand to enter and accumulate in the navigation channel, affecting fishing vessels entering and leaving the port.

Vice Chairman Hoàng inspects the project of building a sand barrier, reducing waves, and dredging the channel into the Sa Huỳnh fishing port's storm shelter anchorage area.
Following the inspection, Vice Chairman Nguyễn Công Hoàng requested the project investor to urgently review and complete documents proposing adjustments to the investment policy, clearly identifying the necessity, effectiveness and proposed additional work.
Any adjustments must meet practical requirements without exceeding the approved total investment.
He assigned the Department of Finance to review the proposal and advise the Provincial People’s Committee in accordance with regulations.
Relevant departments and agencies were also instructed to coordinate in resolving procedures related to the recovery of dredged materials and environmental issues to facilitate the project's next implementation steps.
The provincial leader also inspected the first component of the second phase of the Dung Quất – Sa Huỳnh coastal road project, which has a total investment of nearly VNĐ1.2 trillion and stretches more than 13 kilometres.
Compensation payments to affected residents have reached over 99 per cent.
Some households in An Phú Commune are relocating their homes and structures to clear the site for construction.
Vice Chairman Nguyễn Công Hoàng asked the An Phú Commune authorities to support affected households in relocating and stabilising their lives.
The project investor and contractors were also urged to assist residents in dismantling and moving houses and other structures, accelerate site clearance and ensure construction progress.
M.H