Vice Chairman of Quang Ngai Provincial People’s Committee Tran Phuoc Hien chaired a meeting about the water supply plan for the Hoa Phat Dung Quat 2 Iron and Steel Production Complex.
The project has a total investment of 85,000 billion VND and aims to produce 5.6 million tons of high-quality hot-rolled coil per year.
The company is working to complete the project by 2025 and plans to invest in developing high-quality steel products in the Dung Quat Economic Zone.
They are considering using water from the North Main Canal of the Thach Nham irrigation system to supplement their water source from the Tra Bong River.
In his directions, the Vice Chairman of the Provincial People’s Committee agreed with the plans and technical solutions of Hoa Phat Dung Quat Steel Company regarding the water supply infrastructure for their production complex.
It was emphasized that regulations on water resource management must be followed during the implementation process.
The Authority of Dung Quat Economic Zone and Provincial Industrial Parks was assigned to oversee the project.
M.H